NFPA 110 Testing Schedule Builder

Suggested EPSS Level 1NFPA 110 · Your testing calendar
WEEKLY

EPSS inspection§8.4.1

MONTHLY

30-minute exercise under load§8.4.2

MONTHLY

Transfer-switch operation§8.4.6

ANNUAL

Supplemental load-bank test§8.4.2.4

36-MO

4-hour continuous test§8.4.9

Facility type

Is the generator in service?

Level 1 — failure could cause loss of life or serious injury. Strictest testing and fuel rules, including the 36-month 4-hour test.

Your AHJ or design engineer assigns the official Level, Type and Class — treat this as a starting point.

Full guide: NFPA 110 generator testing requirements

This tool is a planning aid. It does not replace final engineering review, AHJ determination, or a formal quote. Verify requirements with your AHJ and a licensed engineer.